Solar energy in Azerbaijan: regulation and grid connection
In Azerbaijan a home or business solar system is legal, may connect to the grid, and is compensated for surplus energy. The governing statute is Law No. 339-VIQ (31 May 2021), the “active consumer” net-metering scheme is in force (Cabinet Decree No. 346, 28 September 2023), and connection is governed by Decision No. 399 (3 November 2023).
Is a solar system legal in Azerbaijan?
Yes. Homeowners and businesses may install solar for self-consumption on their own roof or land and export the surplus to the grid. Generation below 150 kW needs no generation licence.
Which laws and decisions apply?
The core law is No. 339-VIQ, “On the use of renewable energy sources in electricity production” (31.05.2021). The active-consumer net-metering scheme is Cabinet Decree No. 346 (28.09.2023), grid connection is Decision No. 399 (03.11.2023), and tariffs are set by the Tariff Council.
How does net metering (“active consumer”) work?
In short: a bi-directional meter records export and import, the monthly kWh balance carries to the next month, and a positive year-end balance is compensated. See the net-metering page for detail.
How do I connect a system to Azərişıq?
In short: application → technical conditions → design → connection contract → bi-directional meter → connection act. See the Azərişıq connection page for the step-by-step guide.
Tariffs and savings
Residential tariffs are tiered from January 2025 (8.4 / 10 / 15 qəpik per kWh). Exported surplus is compensated at roughly 8.5 qəpik/kWh, so a system should be sized for self-consumption first.
Permits, 150 kW, and incentives
Generation below 150 kW needs no licence; green-generation tax incentives exist from January 2025, and a household active consumer’s surplus income is tax-free.
Frequently asked questions
Can you connect solar panels to the grid in Azerbaijan?
Yes — connection is governed by Decision No. 399; connected sites register as active consumers and operate with a bi-directional meter.
Do I get paid for surplus energy?
A positive year-end kWh balance is compensated, and for households that income is tax-free. See the net-metering page for the exact figure.
Do I need a licence?
Generation up to 150 kW needs no licence; larger systems fall under licensing.
Sources & last updated
Last updated: 2026-11-26
- Law No. 339-VIQ (31.05.2021), in force from 12.07.2021 — Milli Majlis / e-qanun.az (31.05.2021, In force)
- Active-consumer mechanism — Cabinet Decree No. 346 — Cabinet of Ministers / e-qanun.az (28.09.2023, In force)
- Grid-connection rules — Decision No. 399 — Cabinet of Ministers (e-qanun.az framework 37959) (03.11.2023, In force)
- 150 kW cap (active consumer / unlicensed generation) — AREA / EU4Energy–Ministry of Energy presentation (2025, In force)
Note
This page is general information, not legal advice. Official figures (tariffs, thresholds, fees) can change — verify against the official sources below, or with Azərişıq / ASAN Kommunal, before making a decision.