How to connect your solar system to Azərişıq
Connection of residential and commercial systems is governed by Cabinet Decision No. 399 (3 November 2023). Azərişıq OJSC is the distribution system operator (DSO); applications are handled through Azərişıq offices or ASAN Kommunal. The official per-applicant document checklist is not fully published — the sequence below is the best-sourced reconstruction.
How much is the connection fee?
The connection service fee is set by the Tariff Council, not Azərişıq. A new connection-fee structure took effect on 1 January 2026 (Tariff Council, published 30 December 2025): free/discounted connection in reconstructed networks, graded by capacity and phase — e.g. free for residential and non-residential ≤20 kW single-phase on the existing 0.4 kV grid; a 65% discount for residential >20 kW and non-residential ≤200 kW three-phase.
How long does it take?
Registration/processing of active-consumer status takes ≈ 20 days. The full connection timeline is not officially published.
Where is the official document checklist?
The exact official document checklist, current application form, and standard (non-discounted) fee schedule for active consumers were not found in public sources — confirm these directly with Azərişıq (azerishiq.az) or ASAN Kommunal.
Step-by-step process
- Application — Apply to Azərişıq (office or ASAN Kommunal).
- Technical conditions (texniki şərt) — Technical conditions are issued, setting engineering parameters and the basis for design; prosumers receive an “active consumer’s technical condition”.
- Design documents — Design is prepared per the technical conditions and the 2020 Electrical Installation Rules.
- Connection contract — A connection contract is signed with the DSO and a supply contract with the authorised supplier.
- Bi-directional meter — A bi-directional meter (export + import) is installed at the consumer’s cost.
- Connection act (qoşulma aktı) — Physical connection is confirmed by a connection act.
Frequently asked questions
Which law governs connection?
Cabinet Decision No. 399 (03.11.2023) — rules for connecting construction objects to the electricity network.
Who pays for the meter?
The bi-directional meter is installed at the consumer’s cost.
Is connection free?
In some cases yes — under the 2026 schedule, ≤20 kW single-phase sites on the existing 0.4 kV grid connect free; other categories get a discount. Check the current rate with the Tariff Council / Azərişıq.
Sources & last updated
Last updated: 2026-11-26
- Connection rules — Decision No. 399 — Cabinet of Ministers (e-qanun.az framework 37959) (03.11.2023, In force)
- 2026 connection-fee schedule (free ≤20 kW; 65% discount) — Tariff Council (report.az) (30.12.2025, In force)
- Registration ≈ 20 days — EU4Energy presentation (Nov 2025, In force)
- Azərişıq official services / ASAN Kommunal registration — azerishiq.az / asan.gov.az (2026, In force)
Note
This page is general information, not legal advice. Official figures (tariffs, thresholds, fees) can change — verify against the official sources below, or with Azərişıq / ASAN Kommunal, before making a decision.